You are here: Home › Earthquake Information › Earthquake Info

Road Works - Dallington Area

ROAD  AND FOOTPATH REPAIRS: December 2016 Work is on-going upgrading and sealing footpaths on the following sections of roads in the Dallington Residents Association Area.
The following residents will be affected:  Achillies Street, Rowe Place (off Ajax Street), Banks Avenue, Bampton Street, Barclay Place, Cresswell Avenue and New Brighton Road.  (These are all in the DRA).

Work also will occur on Medway Street, Petrie Street, North Avon Road, Marshland Road and Golf Links Road.

NORTH PARADE:  Work is due to start as of 9th January 2017 on North Parade occurring on the road surface between Banks Avenue and Averill Street.  The traffic flow is controlled by Temporary Traffic Lights and the traffic lights at Averill Street at Shirley Boys High School have been switched off until the work has been completed.  Work on the Footpath and Cycleways outside the Shirley Intermediate School is now complete.

MARSHLAND ROAD:  Work is currently affecting the footpath at The Palms Mall.  Please Take Care!!

Electric Cable Renewal

Electric Cable Renewal:  ORION in conjunction with SCIRT (Stronger Christchurch Infrastructure Rebuild Team) is in the process of laying a new underground heavy duty electric cable of 66,000 volts (66Kv) that will enable power supplies to be fed again to the Dallington Substation in Coopers Road.  The Cable will run from the McFaddens Substation  to the Dallington Substation

Fletcher Construction will lay the cable between the McFaddens Substation to the Corner of Hills Road and Innes Road and McConnell Dowell will lay the remainder of it from the corner of Hills Road and Innes Road via Briggs Road, Olivine Street, Voss Street, Pagoda Street, Joy Street, Golf Links Road, New Brighton Road, Bampton Street and accross Coopers Road to the Substation.

As further information comes to hand I will update you.  (Updated 8th January 2014).


NORTH AVON R0AD - UPGRADE:  Please be aware that the part of NORTH AVON ROAD  between Hills Road and North Parade will be undergoing an upgrade as of Mid January 2018.

We will keep you informed as to what detours are in use (if any) and any road closures that are a part of the project.

This project is expected to take until September 2018 to be fully completed.

CURRENT ROAD CLOSURES:  Chrystal Street at North Avon Road.

Information Correct at Sunday 21st January 2018.

PLEASE NOTE:  This work is not officially in the Dallington Residents Association Boundaries.  However, we believe it is important enough to report to you all on it as many of our residents use North Avon Road.

Some useful links

The Earthquake Commission

The Christchurch City Council

MetroInfo - Bus Information

Canterbury Earthquake


Fletcher Construction